PROJECT SEQUENCE START to FINISH

  • SITE VISIT – Visit and walk the site, take photographs, meet with Owner to learn about his vision for the project, obtain boundary and base maps
  • PRELIMINARY MASTER PLANNING – come up with a Master Plan that best merges the Owner’s vision and the site topography. Rarely achieved in the first attempt, multiple revisions are normal. Depending on the size of the project, may work closely with a Master Planning company
  • COMPLETE PHASE I DESIGN DRAWINGS
  • COMPLETE PHASE II PRELIMINARY DESIGN DRAWINGS
  • COMPLETE PHASE III CONSTRUCTION DRAWINGS
  • BIDDING PROCESS BY APPROVED CONTRACTORS
  • AWARD CONSTRUCTION CONTRACT
  • STAKING – Tee, TP and Green Points correctly colour coded,
    staked and reviewed/approved by AGD
  • NURSERY CONSTRUCTION – in mutually agreed location, construct and plant nursery
  • CLEARING – Removal of all trees, underbrush and weeds from the golf corridor to an initial width of 10m wider than the fairway/bunkers/mounds.
  • GRUBBING – Removal of all stumps, weeds, grasses, branches and other tree debris
  • SURVEYING – Survey and mark all golf course features including tees, bunkers, lake edges, catch basins, mounds and greens. Each survey point to include existing and proposed grades
  • EARTHWORK – excavate all lakes and streams, using this cut material to create golf course features
  • ROUGH SHAPING – preliminary shaping work by AGD approved Shaper to within 15cm of finished grade.
  • LAKE LINING – if deemed necessary (by Project Engineer), line all lakes after rough shaping is approved
  • DRAINAGE – installation of all drainage mainlines, catch basins, lake overflows and outfalls.
  • IRRIGATION – installation of wet well, intake line, pump station, transfer station (if required) and all mainlines, laterals, sprinkler heads and controllers.
  • HARDSCAPING – construction of any rock walls, rock streams, bridges, retaining walls, etc.
  • FEATURES CONSTRUCTION – construction of all tees, bunkers, greens and fairway catch basins.
  • CARTPATH INSTALLATION – construction and pouring of cartpaths, including curbs/drains if required.
  • FINE SHAPING – final shaping of the entire golf course, tieing in all features and cleanup.
  • SAND CAPPING – install grade stakes on each hole prior to sand capping. Final floating with Sand Pro’s and Tractors using Gannon’s, boxblades and/or drag mats.
  • SODDING – all bunker faces, green surrounds and steep slopes must be sodded prior to other grassing procedures.
  • LANDSCAPING – installation of trees, shrubs and other plants at the same time as Sand Capping and Sodding.
  • GRASSING – after AGD reviews/approves the sand capping finish, grassing by either sprigging or hydroseeding. If different grass varieties are involved.
  • GROW-IN – 3-4 month grow-in period that will be deemed complete once AGD Punch List has been completed for each hole.